软土水泥搅拌桩复合地基沉降分析与控制
ANALYSIS AND CONTROL OF COMPOSITE FOUNDATION SETTLEMENT FOR CEMENT MIXING PILES IN SOFT SOIL FOUNDATION
 全文: PDF (0 KB)   HTML (1 KB)  输出: BibTeX | EndNote (RIS)      背景资料
摘要 造成水泥搅拌桩复合地基沉降过大、沉降不均等问题的主要因素有面积置换率、桩长和桩体强度三个方面,应根据实际情况选取合适的面积置换率和水泥掺入比,适当增加桩长能有效控制复合地基的沉降。地基设计时应同时满足承载力和沉降要求,并应以沉降控制为主。
服务
把本文推荐给朋友
加入我的书架
加入引用管理器
E-mail Alert
RSS
作者相关文章
李二兵 丁娜娜 谭跃虎
关键词水泥搅拌桩   沉降控制   桩长     
Abstract: The main factors are the area replacement rate,pile length and pile strength, which are resulted from that the composite foundation settlement is large enough and uneven. The settlement of the composite foundation can effectively controlled by selecting the suitable area replacement rate, the cement mix proportion and suitable pile length according to the actual conditions. The bearing capacity and settlement requirements can be met with the foundation design at the same time.And the settlement control is the dominant.
Key words cement mixing pile   settlement control   pile length   
引用本文:   
李二兵 丁娜娜 谭跃虎. 软土水泥搅拌桩复合地基沉降分析与控制[J]. 建筑技术, 2004, 35(3): 171-172.
LI Erbing DING Nana TAN Yuehu. ANALYSIS AND CONTROL OF COMPOSITE FOUNDATION SETTLEMENT FOR CEMENT MIXING PILES IN SOFT SOIL FOUNDATION[J]. Architecture Technology, 2004, 35(3): 171-172.
链接本文:  
http://www.jzjs.com/CN/     或     http://www.jzjs.com/CN/Y2004/V35/I3/171
 
没有找到本文相关图表信息
没有本文参考文献
[1] 金 平. 复杂软土地基条件下钢结构临时支撑体系设计及施工技术[J]. 建筑技术, 2015, 46(7): 597-.
[2] 张志华. MC劲性复合桩技术在高层住宅工程中的应用[J]. 建筑技术, 2015, 46(6): 532-535.
[3] 董 猛. 复合土钉支护在深圳软件园中的设计应用[J]. 建筑技术, 2012, 43(4): 363-364.
[4] 桂纪平,陈均颐,郭永年,黄彬. 特殊地势深基坑多种围护设计与施工[J]. 建筑工人, 2011, 42(06): 527-530.
[5] 董三升,雷自学,史文智. 黄河中下游冲积平原深长桩极限桩长研究[J]. 建筑工人, 2011, 42(03): 262-265.
?
版权所有 © 2011 建筑技术杂志社
地址:北京市广莲路1号建工大厦A座9层,邮编100055 电话:(010)68512449 (010)63928687,63928688 e-mail:jzjs@sina.com
本系统由北京玛格泰克科技发展有限公司设计开发 技术支持:support@magtech.com.cn