Abstract:
This paper describes a new installation technique for installation of ventilation system at large deformation position of structure. Compared with traditional technique, the new technique could better satisfy the large displacement requirement of structure at position with large deformation, could reach higher aseismic grade and has simpler process, lower cost and higher efficiency. New Kunming Airport terminal building project is taken as an example to describe fabrication, installation form and position layout of ventilation duct at large deformation position of crossing structure and its components, flexible connection, support and hanger, providing valuable references for similar projects.
YAN Wei,LIN Lin,XIE Hui-xue. CONSTRUCTION TECHNIQUE FOR LARGE DEFORMATION POSITION OF VENTILATION
DUCT CROSSING STRUCTURE[J]. Architecture Technology, 2013, 44(8): 723-726.