The shield arriving shaft along the interval between Wangjing West Station and Yongshiying Station of Beijing subway line 17 adopted upside-down hanging side wall excavation method. Considering the large plane area of shield shaft and large burial depth, technical measures were adopted for shaft settlement control and ground water treatment, to guarantee the structural stability and construction
safety of the shaft.
WU Hao. Key Construction Points for Large-Section Upside-down Hanging Side
Wall Shaft Settlement Control and Ground Water Treatment[J]. Architecture Technology, 2018, 49(11): 1163-.