Abstract:
In the reserved Subway Station Engineering of Changzhou Passenger Transport Center, inducing joint is set to divide the station structure into several construction segments longitudinally. Water stop tie and end template are treated to place the concrete in different layers and to guarantee the construction quality of inducing joint. After construction, the fissures of two wallboards are described. The results show that fissures may be emerged intensively in the position of inducing joint when the construction processing is carried out. The measures can not only reduce the fissure amount, but also decrease the engineering cost and seepage-proofing repairs expense.