Abstract:
The main factory building in a power plant of Huainan City adopts plain concrete construction process. In this project, many aspects are improved such as formwork release agent, seam splicing, turning at corner, split bolt, bolt hole, fabrication and reinforcement of formwork, cushion block, fabrication and installation of pre-embedded components, etc. New auxiliary materials are used to realize convenient and fast construction. Repair cost caused by appearance defects of finished concrete products is saved without obviously increasing the construction cost. This construction technique may be promoted and used in plain concrete works of large industrial factory building.