Abstract:
Traffic Hub West Square of Shenzhen North Railway Station is taken as an example to carry out long-term temperature-stress monitoring during construction of super-long concrete floor. Finite element analysis method is used to carry out analog calculation of temperature stress during construction of such structure, and then the calculation result is compared with the actual test result. On basis of the test result and calculation result, distribution law of temperature stress of super-long concrete floor during construction is obtained, namely temperature stress decreases from floor center to floor edges, and related design and construction suggestions are given.
HE Yu-long,LIU Hang,MA Heng et al. TEMPERATURE STRESS TEST AND FINITE ELEMENT ANALYSIS OF
SUPER-LONG CONCRETE FLOOR[J]. Architecture Technology, 2012, 43(1): 41-44.