Abstract:
In Beijing Fortune Plaza Phase II office building project, the core-tube wall on -4 to 20 floors is all-welded steel wall. Concentration of welds and huge heat input cause relatively big stress and obvious welding deformations during welding of the steel plate wall. Therefore, skip block welding, symmetry welding, strict control of welding sequence, setting of deformation control beam and reservation of welding shrinkage allowance are adopted during the construction and reusable welding manipulator is fabricated to basically avoid excessive welding deformation during construction.