Abstract:
Main body of the representative structure in a theme park is found inclined during construction and must be corrected and reinforced. After inspection and analysis of inclination reasons before construction, it is determined to correct the main body inclination by removing the secondary pouring layer of column socle and adjusting the elevation of socle plate according to the characteristics of steel framework. Favorable correction effects are realized.
SONG Ming-zhi,YANG Min,WANG Yong. DESIGN AND CONSTRUCTION FOR DEVIATION-CORRECTION REINFORCEMENT OF STEEL FRAMEWORK STRUCTURE[J]. Architecture Technology, 2012, 43(12): 1130-1133.