Abstract:
During installation of suspension truss in Dalian International Conference Center project, composite floor and structural layers of building are construction after support structures are dismantled, with the purposes to reduce counterforce of temporary support and unloading tonnage in dismantlement of support and to avoid crack caused on concrete of composite floor on surrounding suspension truss due to down-warping deformation of truss. Relevant technical measures are adopted for lifting of platform truss, structure closure, field quality control and dismantlement of support, and construction quality requirements are successfully satisfied.
ZHOU Guang-yi,MAO Li-xian,TANG Jia-ru et al. CONSTRUCTION TECHNIQUE FOR INSTALLATION OF SUSPENSION TRUSS OF DALIAN INTERNATIONAL CONFERENCE CENTER[J]. Architecture Technology, 2013, 44(4): 308-.