Abstract:
The boiler sightseeing platform of Beilun power plant phase III is a spherical point support transparent glass curtain wall. The platform is about 80 meters high of the southwest corner in the steel structure of unit 7. As a result three fourth space of the sightseeing platform are in mid-air, the ball shell installation of glass curtain wall construction is very difficult. In order to guarantee the safety of the construction site, after repeated investigation and scheme comparison and selection, the final selection is to build a temporary suspended construction platform on 67.6m of the boiler steel platform which is beneath of the boiler sightseeing platform. Then the operation scaffold is constructed in the construction of platform. Through the successful construction erection of the platform, the construction of the boiler sightseeing platform finally has been completed satisfactory.