工程实例 |
最新目录 |
下期目录 |
过刊浏览 |
高级检索
|
|
丹江口二桥超长深水墩施工技术研究 |
|
|
|
RESEARCH ON THE CONSTRUCTION TECHNOLOGY OF SUPER-LONG DEEPWATER PIER OF DANJIANGKOU BRIDGE NO. 2 |
|
摘要 丹江口二桥超长深水墩基础施工中,采用将钢护筒与施工平台合二为一的新工艺。施工前进行了计算机模拟分析,确立了施工与监测方案;施工中严格监控,保证了工程质量、进度和安全,取得良好效果。 |
|
关键词: 深水墩
施工平台
模拟施工
|
Abstract:
In the construction of the super-long deepwater pier foundation of Danjiangkou Bridge No. 2, a new technology is employed, that is, integrating the steel protection column with construction platform. Before construction, computer simulation analysis is carried out and the construction and monitoring plan is prepared. In the construction, the project quality, schedule and safety are guaranteed by strict monitoring and control, achieving a good effect.
|
Key words: deepwater pier construction platform construction simulation |
|
引用本文: |
邓铁军 刘永策 张传举. 丹江口二桥超长深水墩施工技术研究[J]. 建筑技术, 2005, 36(2): 125-127.
|
|
|
|
DENG Tiejun LIU Yongce ZHANG Chuanju. RESEARCH ON THE CONSTRUCTION TECHNOLOGY OF SUPER-LONG DEEPWATER PIER OF DANJIANGKOU BRIDGE NO. 2[J]. Architecture Technology, 2005, 36(2): 125-127.
|
链接本文: |
http://www.jzjs.com/CN/ 或 http://www.jzjs.com/CN/Y2005/V36/I2/125 |
|
|
|
|