During construction of seamless connection between Xiaoshan International Airport Phase II project and existing No.1 terminal building, the structure nondestructive dismantlement technique of optically detecting and positioning steel bar plus vibration insulation belt plus diamond core thin wall drill is adopted after consideration of various factors, to effectively solve the technique difficulties in dismantlement of old structures, construction of new structures in the zone. This construction technique successfully dismantles the disused part of the original structure, preserves the useful part and realizes perfect combination between new and old structures, without affecting normal service of No.1 terminal building.
DING Xue-zhi,YANG Yao,MA De-sheng et al. GENERAL CONSTRUCTION TECHNIQUE OF STRUCTURE
NONDESTRUCTIVE DISMANTLEMENT[J]. Architecture Technology, 2014, 45(5): 418-420.