Abstract:
On the basis of analyzing bad influences in metro engineering’s construction schedule management and insufficient in the traditional method, this paper studied how to realize BIM-based construction schedule management of metro engineering to solve existed problems in the present management. Ways to realize BIM-based 4D virtual construction technology, BIM-based graphic construction schedule management, BIM-based visual construction simulation and BIM-based clash detective are raised. By researching a classical metro engineering, feasibility of these methods were verified, and it shows that BIM-based management way which helps to realize integrated management of information is more vivid than traditional way, BIM application improves the efficiency of construction schedule management.
OUYANG Ye-wei,SHI Kai-rong,ZHANG Yuan. Research on Method of BIM-based Construction Schedule Management of Metro Engineering[J]. Architecture Technology, 2017, 48(3): 271-.