Abstract:
Glory Xi'an Financial Center project adopted the core tube and outside frame composite reinforced concrete structure. During selection of construction scheme, the mutual relation among tower crane, formwork climbing, spreader, steel column segmentation and concrete strength was studied according to the structural characteristics of core tube. Construction scheme deployment was designed after comparison of crane installation form, to realize reasonable cooperation among different equipment and to give a full play of the height and lifting capacity advantages of two luffing jib tower cranes. Construction of one standard floor of the core tube was successfully finished for three days.