Abstract:
During steel plate-concrete composite shear wall construction of Glory Xi'an Financial Center, pipelining construction steps and steel structure segmentation were reasonably determined according to the construction structure characteristics with consideration of the following aspects, such as engineering characteristics, technical performance of construction equipment, segmentation of steel structure, structure type, construction process and environment, arrangement and transition time node of tower crane. The transition time of tower crane was effectively used to adjust the construction sequence, successfully realizing continuous construction during tower crane transition and obtaining favorable practical benefits.