Abstract:
During Peijiaying Station construction of Ji'nan subway line R3, key points and difficulties of super-deep foundation pit dewatering project in spring area were analyzed and water pumping test was carried out to obtain relevant hydrologic parameters. This paper designed the dewatering scheme according to geological exploration report, and summarized general process and key points of super-deep foundation pit dewatering construction in spring area.
DING Gui-song,MU Hai-bing,ZHAO Zhen-guo et al. Comparative Analysis of Different Joint Forms of Underground
Continuous Walls in Spring Area[J]. Architecture Technology, 2018, 49(11): 1139-.