Abstract:
In the construction of No.0 section of the prestressed continuous beam of the Raobeihe No.2 Bridge on the Beijing-Fuzhou Railway, the light-duty bracket is used to solve the problem of cantilever casting large-span concrete continuous beam. The force calculation of the bracket system and reasonable structural measures are taken to ensure The quality and construction safety of the
bridge.